• 010-82115891
  • bjhyw@263.net
  • 021-31200158
  • shkehu@263.net

翻译资源

考核计划技术文件翻译中英文对照

1.3.1.3 考核计划Checking Plan
对于技术国产化后的设备将由国外设备供货方和铁道部、业主分别按照下表规定的时间进行考核验收。

Foreign equipment supplier, the Ministry of Railways and employer will jointly check technologically locally made equipment according to the time in the following table.
考核计划表
Checking Plan Table
序号Serial No 名称Name 试验Test 

国外设备供货方确认(评估)confirmed by foreign equipment supplier( evaluation) 

铁道部、业主确认confirmed by the Ministry of Railways and employer
1 GIS开关柜
GIS switch-case

 220KV断路器
220KV circuit breaker
 220KV电动隔离开关
220KV electric disconnecting switch 
 27.5KV系列电动(负荷)隔离开关
27.5 KV serial electric (load) disconnecting switch 

3 绝缘子以内接触网零件
(含补偿装置)
Contact line parts within insulator (including compensation equipment) 2008-3-1~30
4 镁铜合金接触线magnesium copper alloy contact line 
5 铜合金绞线copper alloy stranded conductor 
6 下锚复合绝缘子
Lower anchor combined insulator 
7 Section insulator 

1.3.1.4 保证期
保证期从国产化设备满足性能指标要求,并成功投入商业运营开始计算,期限为两年。
国外设备供货方在保证期内负责对所转让的技术及时进行更新,对存在的不足和缺陷进行补充和更正。
1.3.1.5 Term of Guarantee
The term of guarantee is two years starting when locally made equipment meets requirement of performance index and are successfully put into commercial practice. Foreign equipment supplier is responsible for timely updating transferred technology within the term of guarantee and eliminating existed weak points and demerits.
1.3.2 验收
对于技术国产化的过程,铁道部、业主将对国外设备供货方、国内技术受让企业的国产化情况进行验收。对此,将按照如下验收计划进行验收。
1.4.2 Accepting

As for the process of localization, the Ministry of Railways, employer will check and accept the localization situation of foreign equipment supplier and domestic technology transferee. Examination and accepting will be conducted according to the following table.

华译网北京翻译公司翻译过大量有关考核计划的文件资料,Beijing Chinese Translation Service Company has translated many technical documents about Checking Plan
对于牵引供电材料设备的国产化,必须严格执行有关规定,按照国产化协议认真执行,才能保证国产化过程的顺利实施。也只有通过考核验收的产品,才能真正在武广/广深港客运专线上使用。
The localization of traction power supply materials and equipment must strictly follow relevant regulations and is conscientiously carried out in line with localization agreement so as to ensure the smooth implementation of localization. Only by checking and accepting product, can we put it into practice on Wuguang/Guangshen Port passenger transport special line.
  技术服务
Technological services 

1.是否有详细的国产化阶段技术服务计划。
1. Whether it has detailed technological service plan in the phase of localization.
2.国产化阶段的技术服务与质量监查是否完成。
2. Whether technological services and quality supervision and check in the phase of localization can be completed.
3.技术服务人员是否在每道国产化阶段工序完成后,在国内生产企业的工序表上签字确认。
3. Whether technological service workers can sign and confirm on the procedure table of domestic manufacturing enterprise after completing every phase of localization. 

服务之后一个月内
Within a month after service
  技术培训
Technological training 

1.是否有详细的技术培训计划
1. Whether it has detailed technological training plan.
2.技术培训计划是否完成。
评估合格率达到90%。
2. Whether technological training plan can be completed, with eligibility up to 90%. 

培训完成后一个月内
Within a month after training
  首批产品的质量认可与检查验收
Quality identification, checking and accepting of first group of products 1.国外设备供货方是否对国产化阶段的首批产品进行了质量认可。
1. Whether foreign equipment supplier approves the quality of the first group of products in the phase of localization.
2.国产化阶段的首批产品是否通过了铁道部验收小组的检查验收。
2. Whether the first group of products in the phase of localization has passed the examination and accept of the check team of the Ministry of Railways. 2008年
6月30日前
Before June 30 2008
6 220KV电动隔离开关
220KV electric disconnecting switch
27.5KV系列电动(负荷)隔离开关
27.5 KV serial electric (load) disconnecting switch 技术资料提交
Submitting technological materials 3.国外设备供货方是否依据5.2.1清单提供全部的技术资料。
3. Whether foreign equipment supplier provides all technological materials by 5.2.1 list
1. 国外设备供货方提供的技术资料是否正确、是否清晰,是否能覆盖国产化阶段产品制造的全过程。
4. Whether technological materials provided by foreign equipment supplier are correct, clear and can cover the whole process of product localization.
2. 国外设备供货方提供的技术资料是否能满足国内生产企业根据技术资料制造出及通过国产化阶段产品的型式试验。
5. Whether technological materials provided by foreign equipment supplier can meet the type test approval requirements of products of domestic manufacturing enterprise made according to technological materials and undergo the phase of localization.
 提交技术资料后一个月内
Within a month after submitting technological materials